Project Timeline Estimator

Get a realistic timeline estimate for your renovation project. Understand each phase and factors that can affect your schedule.

1Select Project Type
2Select Factors That Apply

These factors can extend your project timeline. Select all that apply to your project.

Changing layout/moving walls
+2 weeks
Structural modifications (load-bearing)
+3 weeks
Custom cabinets (vs. stock)
+4 weeks
Special order appliances
+2 weeks
Complex permit requirements
+2 weeks
Project Phases for Kitchen Remodeling
1

Design & Planning

1-2 weeks

Finalize design, order materials, pull permits

2

Demolition

2-4 days

Remove old cabinets, countertops, flooring, appliances

3

Rough Work

1-2 weeks

Electrical, plumbing, HVAC modifications

4

Drywall & Paint

1 week

Patch, texture, and paint walls and ceiling

5

Cabinets & Countertops

1-2 weeks

Install cabinets, template and install countertops

6

Finishing

1-2 weeks

Backsplash, appliances, fixtures, flooring, trim

Your Estimated Timeline

Expected Duration

1.5 months - 2.5 months

6-10 weeks total

Project TypeKitchen Remodeling
Base Timeline6-10 weeks
Factors Selected0

Timeline estimates are based on typical projects. Actual duration depends on material availability, permit processing, weather, and project-specific factors.